Tunnel construction in Kuala Lumpur area are to be build due to the increasing traffic congestion in urban areas and increasing land price. Underground structure like tunneling can preserve the land above while providing a route for Mass Rapid Transport (MRT) line for transportation. MRT line in Kuala Lumpur area starts from Sungai Buluh transverse to Kajang. A Cochrane station was to be built underground at the limestone area. TBM method is used for tunneling. A total of 10 TBMs will be used for the construction of tunnels for the 9.5 km underground portion of the Sungai Buluh to Kajang line. The borehole logging method of the area reveals that the limestone rocks of the area have low to moderate strength with approximately 48 MPa to 74 MPa which was determined by unconfined compressive strength test. There are three methods of construction for tunneling such as NATM, cut and cover and rock blasting. It is practically good to used TBM method for tunneling in limestone rock. TBM was designed to handle excavation through the different geological formation. The transitions between the two geological formations in Kuala Lumpur area are such as Kenny Hill formation and karstic limestone are easier by TBM method of underground excavations. The tunneling excavation using TBM was the most suitable for Kuala Lumpur limestone area which have low to moderate strength limestone. TBM has the advantages and disadvantages depending on the type of geological found in that area. Some unforeseen geological condition may delay the rate of penetration of TBM. These unforeseen geological condition may imposed higher cost for the TBM to be repaired. This paper discussed on the suitability of TBM as method of tunneling excavations in limestone rock for underground construction of Cochrane station.

Original languageEnglish
Pages (from-to)2535-2552
Number of pages18
JournalElectronic Journal of Geotechnical Engineering
Volume19 L
Publication statusPublished - 2014

Fingerprint

TBM
Limestone
Rocks
limestone
Excavation
rock
Tunneling (excavation)
excavation
Tunnels
Underground structures
Well logging
Traffic congestion
tunnel
Blasting
project
station
method
borehole logging
cut and cover
NATM

All Science Journal Classification (ASJC) codes

  • Geotechnical Engineering and Engineering Geology

Cite this

@article{7757dda614ac4d3bbf1ab3a69be03f47,
title = "Tunneling in limestone rock using TBM method for MRT projects near cochrane station",
abstract = "Tunnel construction in Kuala Lumpur area are to be build due to the increasing traffic congestion in urban areas and increasing land price. Underground structure like tunneling can preserve the land above while providing a route for Mass Rapid Transport (MRT) line for transportation. MRT line in Kuala Lumpur area starts from Sungai Buluh transverse to Kajang. A Cochrane station was to be built underground at the limestone area. TBM method is used for tunneling. A total of 10 TBMs will be used for the construction of tunnels for the 9.5 km underground portion of the Sungai Buluh to Kajang line. The borehole logging method of the area reveals that the limestone rocks of the area have low to moderate strength with approximately 48 MPa to 74 MPa which was determined by unconfined compressive strength test. There are three methods of construction for tunneling such as NATM, cut and cover and rock blasting. It is practically good to used TBM method for tunneling in limestone rock. TBM was designed to handle excavation through the different geological formation. The transitions between the two geological formations in Kuala Lumpur area are such as Kenny Hill formation and karstic limestone are easier by TBM method of underground excavations. The tunneling excavation using TBM was the most suitable for Kuala Lumpur limestone area which have low to moderate strength limestone. TBM has the advantages and disadvantages depending on the type of geological found in that area. Some unforeseen geological condition may delay the rate of penetration of TBM. These unforeseen geological condition may imposed higher cost for the TBM to be repaired. This paper discussed on the suitability of TBM as method of tunneling excavations in limestone rock for underground construction of Cochrane station.",
author = "{Mohd Pauzi}, {Nur Irfah} and Radhi, {M. S M} and Wong, {Leong Sing} and H. Omar",
year = "2014",
language = "English",
volume = "19 L",
pages = "2535--2552",
journal = "Electronic Journal of Geotechnical Engineering",
issn = "1089-3032",
publisher = "Oklahoma State University",

}

Tunneling in limestone rock using TBM method for MRT projects near cochrane station. / Mohd Pauzi, Nur Irfah; Radhi, M. S M; Wong, Leong Sing; Omar, H.

In: Electronic Journal of Geotechnical Engineering, Vol. 19 L, 2014, p. 2535-2552.

Research output: Contribution to journalArticle

TY - JOUR

T1 - Tunneling in limestone rock using TBM method for MRT projects near cochrane station

AU - Mohd Pauzi, Nur Irfah

AU - Radhi, M. S M

AU - Wong, Leong Sing

AU - Omar, H.

PY - 2014

Y1 - 2014

N2 - Tunnel construction in Kuala Lumpur area are to be build due to the increasing traffic congestion in urban areas and increasing land price. Underground structure like tunneling can preserve the land above while providing a route for Mass Rapid Transport (MRT) line for transportation. MRT line in Kuala Lumpur area starts from Sungai Buluh transverse to Kajang. A Cochrane station was to be built underground at the limestone area. TBM method is used for tunneling. A total of 10 TBMs will be used for the construction of tunnels for the 9.5 km underground portion of the Sungai Buluh to Kajang line. The borehole logging method of the area reveals that the limestone rocks of the area have low to moderate strength with approximately 48 MPa to 74 MPa which was determined by unconfined compressive strength test. There are three methods of construction for tunneling such as NATM, cut and cover and rock blasting. It is practically good to used TBM method for tunneling in limestone rock. TBM was designed to handle excavation through the different geological formation. The transitions between the two geological formations in Kuala Lumpur area are such as Kenny Hill formation and karstic limestone are easier by TBM method of underground excavations. The tunneling excavation using TBM was the most suitable for Kuala Lumpur limestone area which have low to moderate strength limestone. TBM has the advantages and disadvantages depending on the type of geological found in that area. Some unforeseen geological condition may delay the rate of penetration of TBM. These unforeseen geological condition may imposed higher cost for the TBM to be repaired. This paper discussed on the suitability of TBM as method of tunneling excavations in limestone rock for underground construction of Cochrane station.

AB - Tunnel construction in Kuala Lumpur area are to be build due to the increasing traffic congestion in urban areas and increasing land price. Underground structure like tunneling can preserve the land above while providing a route for Mass Rapid Transport (MRT) line for transportation. MRT line in Kuala Lumpur area starts from Sungai Buluh transverse to Kajang. A Cochrane station was to be built underground at the limestone area. TBM method is used for tunneling. A total of 10 TBMs will be used for the construction of tunnels for the 9.5 km underground portion of the Sungai Buluh to Kajang line. The borehole logging method of the area reveals that the limestone rocks of the area have low to moderate strength with approximately 48 MPa to 74 MPa which was determined by unconfined compressive strength test. There are three methods of construction for tunneling such as NATM, cut and cover and rock blasting. It is practically good to used TBM method for tunneling in limestone rock. TBM was designed to handle excavation through the different geological formation. The transitions between the two geological formations in Kuala Lumpur area are such as Kenny Hill formation and karstic limestone are easier by TBM method of underground excavations. The tunneling excavation using TBM was the most suitable for Kuala Lumpur limestone area which have low to moderate strength limestone. TBM has the advantages and disadvantages depending on the type of geological found in that area. Some unforeseen geological condition may delay the rate of penetration of TBM. These unforeseen geological condition may imposed higher cost for the TBM to be repaired. This paper discussed on the suitability of TBM as method of tunneling excavations in limestone rock for underground construction of Cochrane station.

UR - http://www.scopus.com/inward/record.url?scp=84901294442&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84901294442&partnerID=8YFLogxK

M3 - Article

AN - SCOPUS:84901294442

VL - 19 L

SP - 2535

EP - 2552

JO - Electronic Journal of Geotechnical Engineering

JF - Electronic Journal of Geotechnical Engineering

SN - 1089-3032

ER -