Relationship between loss of load expectation and reserve margin for optimal generation planning

Research output: Contribution to journalArticle

1 Citation (Scopus)

Abstract

Generation planning utilizes reliability indices as criteria to ensure adequacy in terms of total installed capacity. Reserve Margin and Loss of Load Expectation (LOLE) are the most widely-used indices in generation adequacy evaluation. Reserve Margin is a measure of available capacity over and above the capacity needed to meet normal peak demand levels. In Peninsular Malaysia, the amount of Reserve Margin has been perceived to be high. Generally, high Reserve Margin can provide high reliability. However, it acquires more generation plant, for which some of them may not be necessary. This may indicate over investment which will be reflected in the tariff structure. LOLE is a probabilistic measure which indicates the risk at which the generation capacity fails to meet the demand and its evaluation involves specific parameters such as the plant capacity and outage rate of each generating unit. Therefore, in order to have optimum generation planning and investment efficiency, it is necessary to perform a study on the practical Reserve Margin level with respect to the current LOLE requirement without endangering the overall power system reliability. This research studies the factors affecting LOLE and evaluates the relationship between Reserve Margin and LOLE under various conditions. A modified Peninsular Malaysia system is simulated using Wien Automatic System Planning (WASP -IV) to determine LOLE focusing on thermal power plants. This study concludes that peak load and forced outage rate give significant impacts to the LOLE and thus, the reliability of the system. Effort to ensure availability especially during peak load may need to be intensified. The study also establishes an inverse exponential curve for the relationship between Reserve Margin and LOLE. It is found that the outcome of the study is to enhance generation planning decision making in obtaining the optimum Reserve Margin considering the LOLE under various conditions.

Original languageEnglish
Pages (from-to)27-33
Number of pages7
JournalJurnal Teknologi
Volume78
Issue number5-9
DOIs
Publication statusPublished - 01 Jan 2016

Fingerprint

Electric load loss
Planning
Outages
Power plants
Decision making
Availability

All Science Journal Classification (ASJC) codes

  • Engineering(all)

Cite this

@article{ae8af05d612c47feb8c835edcfea3a55,
title = "Relationship between loss of load expectation and reserve margin for optimal generation planning",
abstract = "Generation planning utilizes reliability indices as criteria to ensure adequacy in terms of total installed capacity. Reserve Margin and Loss of Load Expectation (LOLE) are the most widely-used indices in generation adequacy evaluation. Reserve Margin is a measure of available capacity over and above the capacity needed to meet normal peak demand levels. In Peninsular Malaysia, the amount of Reserve Margin has been perceived to be high. Generally, high Reserve Margin can provide high reliability. However, it acquires more generation plant, for which some of them may not be necessary. This may indicate over investment which will be reflected in the tariff structure. LOLE is a probabilistic measure which indicates the risk at which the generation capacity fails to meet the demand and its evaluation involves specific parameters such as the plant capacity and outage rate of each generating unit. Therefore, in order to have optimum generation planning and investment efficiency, it is necessary to perform a study on the practical Reserve Margin level with respect to the current LOLE requirement without endangering the overall power system reliability. This research studies the factors affecting LOLE and evaluates the relationship between Reserve Margin and LOLE under various conditions. A modified Peninsular Malaysia system is simulated using Wien Automatic System Planning (WASP -IV) to determine LOLE focusing on thermal power plants. This study concludes that peak load and forced outage rate give significant impacts to the LOLE and thus, the reliability of the system. Effort to ensure availability especially during peak load may need to be intensified. The study also establishes an inverse exponential curve for the relationship between Reserve Margin and LOLE. It is found that the outcome of the study is to enhance generation planning decision making in obtaining the optimum Reserve Margin considering the LOLE under various conditions.",
author = "{Muhamad Zafir}, {Siti Rasheeka} and {Muhamad Razali}, {Noor Miza} and {Tengku Hashim}, {Tengku Juhana}",
year = "2016",
month = "1",
day = "1",
doi = "10.11113/jt.v78.8783",
language = "English",
volume = "78",
pages = "27--33",
journal = "Jurnal Teknologi (Sciences and Engineering)",
issn = "0127-9696",
publisher = "Penerbit Universiti Teknologi Malaysia",
number = "5-9",

}

Relationship between loss of load expectation and reserve margin for optimal generation planning. / Muhamad Zafir, Siti Rasheeka; Muhamad Razali, Noor Miza; Tengku Hashim, Tengku Juhana.

In: Jurnal Teknologi, Vol. 78, No. 5-9, 01.01.2016, p. 27-33.

Research output: Contribution to journalArticle

TY - JOUR

T1 - Relationship between loss of load expectation and reserve margin for optimal generation planning

AU - Muhamad Zafir, Siti Rasheeka

AU - Muhamad Razali, Noor Miza

AU - Tengku Hashim, Tengku Juhana

PY - 2016/1/1

Y1 - 2016/1/1

N2 - Generation planning utilizes reliability indices as criteria to ensure adequacy in terms of total installed capacity. Reserve Margin and Loss of Load Expectation (LOLE) are the most widely-used indices in generation adequacy evaluation. Reserve Margin is a measure of available capacity over and above the capacity needed to meet normal peak demand levels. In Peninsular Malaysia, the amount of Reserve Margin has been perceived to be high. Generally, high Reserve Margin can provide high reliability. However, it acquires more generation plant, for which some of them may not be necessary. This may indicate over investment which will be reflected in the tariff structure. LOLE is a probabilistic measure which indicates the risk at which the generation capacity fails to meet the demand and its evaluation involves specific parameters such as the plant capacity and outage rate of each generating unit. Therefore, in order to have optimum generation planning and investment efficiency, it is necessary to perform a study on the practical Reserve Margin level with respect to the current LOLE requirement without endangering the overall power system reliability. This research studies the factors affecting LOLE and evaluates the relationship between Reserve Margin and LOLE under various conditions. A modified Peninsular Malaysia system is simulated using Wien Automatic System Planning (WASP -IV) to determine LOLE focusing on thermal power plants. This study concludes that peak load and forced outage rate give significant impacts to the LOLE and thus, the reliability of the system. Effort to ensure availability especially during peak load may need to be intensified. The study also establishes an inverse exponential curve for the relationship between Reserve Margin and LOLE. It is found that the outcome of the study is to enhance generation planning decision making in obtaining the optimum Reserve Margin considering the LOLE under various conditions.

AB - Generation planning utilizes reliability indices as criteria to ensure adequacy in terms of total installed capacity. Reserve Margin and Loss of Load Expectation (LOLE) are the most widely-used indices in generation adequacy evaluation. Reserve Margin is a measure of available capacity over and above the capacity needed to meet normal peak demand levels. In Peninsular Malaysia, the amount of Reserve Margin has been perceived to be high. Generally, high Reserve Margin can provide high reliability. However, it acquires more generation plant, for which some of them may not be necessary. This may indicate over investment which will be reflected in the tariff structure. LOLE is a probabilistic measure which indicates the risk at which the generation capacity fails to meet the demand and its evaluation involves specific parameters such as the plant capacity and outage rate of each generating unit. Therefore, in order to have optimum generation planning and investment efficiency, it is necessary to perform a study on the practical Reserve Margin level with respect to the current LOLE requirement without endangering the overall power system reliability. This research studies the factors affecting LOLE and evaluates the relationship between Reserve Margin and LOLE under various conditions. A modified Peninsular Malaysia system is simulated using Wien Automatic System Planning (WASP -IV) to determine LOLE focusing on thermal power plants. This study concludes that peak load and forced outage rate give significant impacts to the LOLE and thus, the reliability of the system. Effort to ensure availability especially during peak load may need to be intensified. The study also establishes an inverse exponential curve for the relationship between Reserve Margin and LOLE. It is found that the outcome of the study is to enhance generation planning decision making in obtaining the optimum Reserve Margin considering the LOLE under various conditions.

UR - http://www.scopus.com/inward/record.url?scp=84970959727&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84970959727&partnerID=8YFLogxK

U2 - 10.11113/jt.v78.8783

DO - 10.11113/jt.v78.8783

M3 - Article

VL - 78

SP - 27

EP - 33

JO - Jurnal Teknologi (Sciences and Engineering)

JF - Jurnal Teknologi (Sciences and Engineering)

SN - 0127-9696

IS - 5-9

ER -